|POR|DE| 

Customer enquiry management acts as a first filter which undertakes some coarse smoothing of the planned workload. This workload smoothing or load balancing corresponds to one of the main principles of heijunka in lean operations and prevents surges in work which temporarily deplete the capacity buffer and increase the inventory buffer in the form of work-in-process. The principle of heijunka relates to leveling peaks and troughs in the production schedule, thereby creating some stability in the workload through balancing. Creating this stability has been argued to be the only way of realistically creating a continuous flow. 

Customer enquiry management consists of three inter-dependent parts:

Workload Control supports managers to effectively use the inventory, capacity and lead time buffer through the simultaneous control of inventory, capacity and lead time, integrating production and sales into a hierarchical system of workloads. The hierarchy of workloads consists of: the shop floor workload; the planned workload; and, the total workload.

The three elements of customer enquiry management provide a company with the tools to bridge the commonly encountered production/sales divide caused by the conflicting objectives of these two functions. On the one hand, the sales department wants to maximize sales revenue (i.e. the strike rate) by quoting often unrealistically short due dates and prices. On the other hand, the production department pushes for a high backlog and longer lead times to create a continuous flow on the shop floor. 

The forward/backward scheduling element can be used to set or assess the feasibility of due dates and incurred production costs to ensure quotes are competitive but with realistic due dates and prices which reflect the actual operational capabilities of the firm. A set of decision criteria – e.g. the expected profit - can then be developed based on the strike rate analysis to support the bidding process. This allows profitability to be maintained while controlling the planned workload (i.e. the workload on the shop floor and in the pool) through realistic due dates.  

From an operational point of view, this provides a control loop that: (i) reduces variability – as the incoming workload is controlled – allowing the capacity buffer to be minimized; and, (ii) regulates the ‘over-booking’ strategy of a company necessary for ensuring the utilization of scarce capacity. For example: When the workload starts to increase, the lead times that can be realistically offered become longer – this reduces the strike rate of the company and, therefore, its workload. Then, as the workload decreases, the lead times that can be realistically offered start to shorten – this improves the strike rate and, therefore, increases the workload. 

Key Definitions

Forward Scheduling (Due Date Setting)

A feasible due date is determined by forward scheduling from the earliest release date, i.e. the date by which an order is expected to have been confirmed and materials made available. 

The forward scheduling methodology presented here matches required and available capacity overtime. It bases on the methodology presented by Bertrand (1983a) and (1983b) and Bechte (1994) and has been chosen due to its outstanding performance compared to alternative rules suitable for high variable production environments as typical for small to medium sized make-to-order companies (see Thürer et al., 2012b). 

For the method presented here a dynamic factor to allow for the queuing time F(W,C) that is dependent on both the cumulative total workload (W) and capacity (C) until a future time bucket at the work center which performs a certain operation is added to the operation due date of the job that would otherwise be determined based on infinite capacity. The operation due date based on infinite capacity is given by the operation due date of the previous operation (ODDi-1)plus the processing time (p) of the job.  The starting operation due date is given by the earliest release date plus an estimate for the expected pool waiting  time. Following Little's Law, this expected waiting time pior to release can be indicated by the workload waiting in the pool for the work center that is more likely to restrict the release possibilities; i.e. the work center with the maximum pool load across the work center(s) in the routing of the order (see also COBACABANA).

To determine the queuing time allowance factor F(W,C), first the actual cumulative workload and capacity in each time bucket are determined for each work center. Next, and starting with the first work center in the routing of a job, the queuing time allowance factor is determined as follows (see also Figure):

This procedure is repeated at the next work center in the routing of the job until all operation due dates have been determined, with the last operation due date becoming the due date of the order. 

 Note that the due date determined presents the internal or production due date. This due date represents the current production capability. To account for variability during production (which will always occur) an extra time buffer has to be added to obtain the lead time to be quoted to the customer. This so-called external lead time buffer allows management to determine the service level to be achieved (see e.g. Enns, 1995; Hopp & Sturgis, 2000). 


Backward Scheduling (Due Date Feasibility) 

The feasibility of a due date specified by a customer is determined by backward scheduling to find a latest release date, i.e. the date by which the order must be released from the pre-shop pool if it is to be delivered to the customer on time. 

Under backward scheduling (assuming capacity to be finite), the required capacity at each work center is loaded into the available capacity as done for forward scheduling above except the procedure works backwards from a given due date. Three options have been presented in the literature for handling an overload (i.e. backward scheduling that results in a latest released date prior to the earliest release date): 


Strike Rate Analysis

An make-to-order company’s future workload is dependent on the number of tenders or quotations that are converted into firm orders: the strike rate.  A simple two-step process for developing a matrix that links strike rates to a set of outcomes was developed in the literature (see Kingsman et al., 1993, 1996; Kingsman & Mercer, 1997): 

(i) the company’s order winning history for each type of order is used to cluster similar orders – for example, in the Figure the overall strike rate is about 54% but for larger orders it is about 66%, and this type of order can be further subdivided into high value and low value orders with a strike rate of about 18% and 72%, respectively; then

 (ii) a matrix of cells with e.g. the class of due date on the x axis and the class of mark-up (i.e. the price minus the incurred cost) on the y axis is created for each cluster to record its order winning history and link strike rates to certain sets of outcomes 

This matrix of order winning history is updated as more historical data becomes available, i.e. after each acceptance/rejection decision. If the company wins a tender, then the value in the cell corresponding to that set of outcomes (e.g. due date and mark-up) is increased by one. But as the company would also have likely won the tender with a more competitive bid (e.g. a lower price or earlier due date), cells with a lower mark-up and/or due date are also increased by one (see the shaded area in the Figure). The strike rate for a certain set of outcomes can then be estimated as the quotient of the value in the corresponding cells and the total number of bids or tenders. 

 

Forward/Backward Scheduling & Strike Rate Estimation  

The forward/backward scheduling element of CEM can be used to set or assess the feasibility of due dates and incurred production costs to ensure quotes are competitive but with realistic due dates and prices which reflect the actual operational capabilities of the firm. A set of decision criteria – e.g. the expected profit, given by the mark-up multiplied by the strike rate estimate – can then be developed using the matrix of order winning history to support the bidding process. This allows profitability to be maintained while controlling the planned workload through realistic due dates. 

From an operational point of view, this provides a control loop that: (i) reduces variability – as the incoming workload is controlled – allowing the capacity buffer to be minimized; and, (ii) regulates the ‘over-booking’ strategy of a company necessary for ensuring the utilization of scarce capacity. More specifically, forward/backward scheduling and strike rates interact as follows: 

Thus, customer enquiry management acts as a first filter which undertakes some coarse smoothing of the planned workload. This workload smoothing or load balancing corresponds to one of the main principles of heijunka in lean operations which relates to leveling peaks and troughs in the production schedule, thereby creating some stability in the workload through balancing. Creating this stability has been argued to be the only way of realistically creating a continuous flow (e.g. Liker & Meier, 2006) and facilitates subsequent control tasks as order release and shop floor dispatching.